Known Issue 298
Project Completion and Project Phase fields are ignored for Builder's Risk exposure when running precipitation flood only in the Verisk Hurricane Model for the United States.
| Issue ID | 298 |
| Summary | Project Completion and Project Phase fields are ignored for Builder's Risk exposure when running precipitation flood only in the Verisk Hurricane Model for the United States. |
| Description | Some locations may not see this issue even if this criteria is met if the event intensity is not in a certain range. Wind and Surge modules in the Verisk Hurricane Model for the United States are not affected by this issue. |
| Resolved in | |
| Date posted | 7/10/2020 |
| Software versions affected | 11.2, 11.0, 10.0, 9.1, 9.0 |
| Feature set | Detailed loss |
| Models | Verisk Hurricane Model for the United States |
| Potential for loss numbers impact | Yes |
| Workaround | Run Builder's Risk exposures with all sub-perils. |